{"id":30652,"date":"2018-07-06T12:33:32","date_gmt":"2018-07-06T16:33:32","guid":{"rendered":"https:\/\/www.pmvision.ca\/?p=30652"},"modified":"2018-12-15T00:40:01","modified_gmt":"2018-12-15T04:40:01","slug":"microsoft-project-2016-resources-with-multiple-pay-rates","status":"publish","type":"post","link":"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/","title":{"rendered":"Microsoft Project 2016 | Resources With Multiple Pay Rates"},"content":{"rendered":"<p>In projects, you can have a single resource with multiple pay rates.\u00a0 Some resources might perform different tasks with different pay rates. Or, you may have a situation where a single resource has differing pay rates over time. In Microsoft Project You can set up different pay rates for the same resource, and then specify which rate to use per assignment.<\/p>\n<p>For example, in the new construction project, the project coordinator could also serve as a scheduler. Because the costs for project coordinator and project scheduler are different, you can set up two cost rate tables for the resource (additionally, a cost rate table can include a standard pay rate and an optional overtime rate, and even a per-use cost). Then, after you assign the resource to tasks, you specify which pay rate should apply.<\/p>\n<p>When defining the resource in Microsoft project, each work or material resource can have up to five different pay rates, each recorded in a cost rate table. Cost rate table A is the default. Use a resource note to help document each role\u2019s pay rate.<\/p>\n<p>You set up pay rates in the cost rate tables on the Costs tab of the Resource Information dialog box. The default rate table (the rate Project applies unless you specify another one) is on tab A.<\/p>\n<h4><\/h4>\n<h2><span style=\"color: #008080;\"><strong>To create an additional cost rate table for a resource<\/strong><\/span><\/h2>\n<ol>\n<li>On the <strong>View <\/strong>tab, in the <strong>Resource Views <\/strong>group, click <strong>Resource Sheet<\/strong>.<\/li>\n<li>In the Resource Sheet view, click a resource name.<\/li>\n<li>On the <strong>Resource <\/strong>tab, in the <strong>Properties <\/strong>group, click <strong>Information <\/strong>to open the Resource Information dialog box.<\/li>\n<li>Click the <strong>Costs <\/strong>tab.<\/li>\n<li>In the <strong>Cost rate tables <\/strong>area, click the <strong>B C<\/strong>, <strong>D<\/strong>, or <strong>E <\/strong>tab.<\/li>\n<li>In the <strong>Standard Rate <\/strong>and <strong>Overtime Rate <\/strong>fields, enter the pay rate values you want. In addition to or instead of pay rates, you can also enter a value in the <strong>Per Use <\/strong><strong>Cost <\/strong>field.<\/li>\n<li>Click <strong>OK <\/strong>to close the Resource Information dialog box.<\/li>\n<\/ol>\n<blockquote><p><a href=\"http:\/\/www.pmvision.ca\/global\/shop\/microsoft-project-training-courses-toronto\/\" target=\"_blank\" rel=\"noopener\">Learn MS.Project 2016\u00a0 Fundamentals in Toronto, Mississauga, Scarborough, Ottawa, &amp; Montreal<\/a><\/p>\n<p><a href=\"http:\/\/www.pmvision.ca\/global\/shop\/advanced-microsoft-project-training-course\/\" target=\"_blank\" rel=\"noopener\">Learn Advanced Techniques in MS.Project 2016\u00a0 in Toronto, Mississauga, Scarborough, Ottawa, &amp; Montreal<\/a><\/p><\/blockquote>\n<h2><\/h2>\n<h2><span style=\"color: #008080;\"><strong>Example:<\/strong><\/span><\/h2>\n<p>In the following Figure we have the resource sheet including our demonstration work resource, John Sloan.<\/p>\n<p><a href=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-1-Resources-Sheet.jpg\"><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" class=\"size-large wp-image-30653\" src=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-1-Resources-Sheet.jpg?resize=1024%2C407\" alt=\"Microsoft Project 2016- Resource with multiple pay\" width=\"1024\" height=\"407\" srcset=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-1-Resources-Sheet.jpg?resize=1024%2C407&amp;ssl=1 1024w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-1-Resources-Sheet.jpg?resize=150%2C60&amp;ssl=1 150w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-1-Resources-Sheet.jpg?resize=300%2C119&amp;ssl=1 300w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-1-Resources-Sheet.jpg?resize=768%2C305&amp;ssl=1 768w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-1-Resources-Sheet.jpg?resize=1080%2C429&amp;ssl=1 1080w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-1-Resources-Sheet.jpg?resize=800%2C318&amp;ssl=1 800w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-1-Resources-Sheet.jpg?w=1365&amp;ssl=1 1365w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><\/a><\/p>\n<p>&nbsp;<\/p>\n<p>John has a standard pay rate of $75\/hr. We want to define an additional pay rate for John. We proceed and select the resource tab and information icon.<\/p>\n<p><a href=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs1.jpg\"><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" class=\"aligncenter size-large wp-image-30654\" src=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs1.jpg?resize=1024%2C418\" alt=\"\" width=\"1024\" height=\"418\" srcset=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs1.jpg?resize=1024%2C418&amp;ssl=1 1024w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs1.jpg?resize=150%2C61&amp;ssl=1 150w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs1.jpg?resize=300%2C122&amp;ssl=1 300w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs1.jpg?resize=768%2C313&amp;ssl=1 768w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs1.jpg?resize=1080%2C441&amp;ssl=1 1080w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs1.jpg?resize=800%2C326&amp;ssl=1 800w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs1.jpg?w=1365&amp;ssl=1 1365w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><\/a><\/p>\n<p>In the resource information dialog, we choose the cost tab and default cost rate table A. Note that our standard rate, $75\/hr. This default cost rate, A, is the cost when our resource , John,is working as a Project Coordinator.<\/p>\n<p><a href=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs-A.jpg\"><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" class=\"aligncenter size-large wp-image-30655\" src=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs-A.jpg?resize=1024%2C418\" alt=\"Microsoft Project 2016 - Resource costs\" width=\"1024\" height=\"418\" srcset=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs-A.jpg?resize=1024%2C418&amp;ssl=1 1024w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs-A.jpg?resize=150%2C61&amp;ssl=1 150w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs-A.jpg?resize=300%2C122&amp;ssl=1 300w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs-A.jpg?resize=768%2C313&amp;ssl=1 768w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs-A.jpg?resize=1080%2C441&amp;ssl=1 1080w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs-A.jpg?resize=800%2C326&amp;ssl=1 800w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-2-Resources-Information-Costs-A.jpg?w=1365&amp;ssl=1 1365w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><\/a><\/p>\n<p>Then we choose the cost rate table B, and enter a standard rate, $60\/hr, for our resource\u2019s Scheduler role.<\/p>\n<p><a href=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Costs-2.jpg\"><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" class=\"aligncenter size-large wp-image-30657\" src=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Costs-2.jpg?resize=1024%2C418\" alt=\"Microsoft Project 2016- Managing Resource costs\" width=\"1024\" height=\"418\" srcset=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Costs-2.jpg?resize=1024%2C418&amp;ssl=1 1024w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Costs-2.jpg?resize=150%2C61&amp;ssl=1 150w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Costs-2.jpg?resize=300%2C122&amp;ssl=1 300w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Costs-2.jpg?resize=768%2C313&amp;ssl=1 768w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Costs-2.jpg?resize=1080%2C441&amp;ssl=1 1080w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Costs-2.jpg?resize=800%2C326&amp;ssl=1 800w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Costs-2.jpg?w=1365&amp;ssl=1 1365w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><\/a><div class='et-box et-shadow'>\n\t\t\t\t\t<div class='et-box-content'>Create up to five different cost rate tables (including standard and overtime rates, and per-use cost) on the Costs tab of the Resource Information dialog box<\/div><\/div><\/p>\n<p>&nbsp;<\/p>\n<p>Choose the notes tab to document the pay rate of each role, Coordinator and Scheduler.<\/p>\n<p><a href=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Notes.jpg\"><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" class=\"aligncenter size-large wp-image-30658\" src=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Notes.jpg?resize=1024%2C404\" alt=\"Microsoft Project 2016- Managing Resource costs notes\" width=\"1024\" height=\"404\" srcset=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Notes.jpg?resize=1024%2C404&amp;ssl=1 1024w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Notes.jpg?resize=150%2C59&amp;ssl=1 150w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Notes.jpg?resize=300%2C118&amp;ssl=1 300w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Notes.jpg?resize=768%2C303&amp;ssl=1 768w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Notes.jpg?resize=1080%2C426&amp;ssl=1 1080w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Notes.jpg?resize=800%2C315&amp;ssl=1 800w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-3-Resources-Information-Notes.jpg?w=1365&amp;ssl=1 1365w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><\/a><\/p>\n<p>Note the resource sheet and John\u2019s resource note.<\/p>\n<p><a href=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-5-Resources-Sheet.jpg\"><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" class=\"aligncenter size-large wp-image-30659\" src=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-5-Resources-Sheet.jpg?resize=1024%2C387\" alt=\"Microsoft Project 2016- Managing Resource Sheet\" width=\"1024\" height=\"387\" srcset=\"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-5-Resources-Sheet.jpg?resize=1024%2C387&amp;ssl=1 1024w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-5-Resources-Sheet.jpg?resize=150%2C57&amp;ssl=1 150w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-5-Resources-Sheet.jpg?resize=300%2C113&amp;ssl=1 300w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-5-Resources-Sheet.jpg?resize=768%2C290&amp;ssl=1 768w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-5-Resources-Sheet.jpg?resize=1080%2C408&amp;ssl=1 1080w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-5-Resources-Sheet.jpg?resize=800%2C302&amp;ssl=1 800w, https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-5-Resources-Sheet.jpg?w=1365&amp;ssl=1 1365w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><\/a><\/p>\n<h4><\/h4>\n<h2><span style=\"color: #008080;\"><strong>To change the cost rate table to be applied to an assignment<\/strong><\/span><\/h2>\n<ol>\n<li>Do either of the following:<\/li>\n<\/ol>\n<ul>\n<li>On the <strong>View <\/strong>tab, in the <strong>Task Views <\/strong>group, click <strong>Task Usage<\/strong>.<\/li>\n<li>On the <strong>View <\/strong>tab, in the <strong>Resource Views <\/strong>group, click <strong>Resource Usage<\/strong>.<\/li>\n<\/ul>\n<p>As with other assignment-level activities, you can perform this procedure in either view.<\/p>\n<ol start=\"2\">\n<li>Select the assignment you want to edit.<\/li>\n<li>On the <strong>Format <\/strong>tab, in the <strong>Assignment <\/strong>group, click <strong>Information <\/strong>to open the Assignment Information dialog box. Click the <strong>General <\/strong>tab if it is not already selected.<\/li>\n<\/ol>\n<ol start=\"4\">\n<li>In the <strong>Cost Rate Table <\/strong>box, select a cost rate table, and then click <strong>OK <\/strong>to close the Assignment Information dialog box.<\/li>\n<\/ol>\n<div class='et-box et-shadow'>\n\t\t\t\t\t<div class='et-box-content'>If you frequently change cost rate tables for assignments, you will find it quicker to display the Cost Rate Table field directly in the Resource Usage or Task Usage view. To do so, display the right edge of the table portion of a usage view, click Add New Column, and then select Cost Rate Table.<\/div><\/div>\n<p>&nbsp;<\/p>\n<blockquote><p><a href=\"http:\/\/www.pmvision.ca\/global\/shop\/microsoft-project-training-courses-toronto\/\" target=\"_blank\" rel=\"noopener\">Take our MS.Project 2016 Fundamentals Training Class in Toronto, Mississauga, Scarborough, Ottawa, &amp; Montreal<\/a><\/p>\n<p><a href=\"http:\/\/www.pmvision.ca\/global\/shop\/advanced-microsoft-project-training-course\/\" target=\"_blank\" rel=\"noopener\">Take our Advanced MS.Project 2016\u00a0Training Courses in Toronto, Mississauga, Scarborough, Ottawa, &amp; Montreal<\/a><\/p><\/blockquote>\n","protected":false},"excerpt":{"rendered":"<p>In projects, you can have a single resource with multiple pay rates.\u00a0 Some resources might perform different tasks with different pay rates. Or, you may have a situation where a single resource has differing pay rates over time. In Microsoft Project You can set up different pay rates for the same resource, and then specify [&hellip;]<\/p>\n","protected":false},"author":354,"featured_media":0,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_jetpack_newsletter_access":"","_jetpack_dont_email_post_to_subs":false,"_jetpack_newsletter_tier_id":0,"_jetpack_memberships_contains_paywalled_content":false,"_jetpack_feature_clip_id":0,"_jetpack_memberships_contains_paid_content":false,"footnotes":"","jetpack_post_was_ever_published":false},"categories":[65,18],"tags":[],"class_list":["post-30652","post","type-post","status-publish","format-standard","hentry","category-ms-project","category-pm"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v28.7 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Microsoft Project 2016 | Resources With Multiple Pay Rates<\/title>\n<meta name=\"description\" content=\"In projects, you can have a single resource with multiple pay rates. Some resources might perform different tasks with different pay rates.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Microsoft Project 2016 | Resources With Multiple Pay Rates\" \/>\n<meta property=\"og:description\" content=\"In projects, you can have a single resource with multiple pay rates. Some resources might perform different tasks with different pay rates.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/\" \/>\n<meta property=\"og:site_name\" content=\"PMVISION Global\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/pmvisioninc\" \/>\n<meta property=\"article:published_time\" content=\"2018-07-06T16:33:32+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2018-12-15T04:40:01+00:00\" \/>\n<meta property=\"og:image\" content=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-1-Resources-Sheet-1024x407.jpg\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:creator\" content=\"@pmvisioninc\" \/>\n<meta name=\"twitter:site\" content=\"@pmvisioninc\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"4 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/microsoft-project-2016-resources-with-multiple-pay-rates\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/microsoft-project-2016-resources-with-multiple-pay-rates\\\/\"},\"author\":{\"name\":\"\",\"@id\":\"\"},\"headline\":\"Microsoft Project 2016 | Resources With Multiple Pay Rates\",\"datePublished\":\"2018-07-06T16:33:32+00:00\",\"dateModified\":\"2018-12-15T04:40:01+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/microsoft-project-2016-resources-with-multiple-pay-rates\\\/\"},\"wordCount\":714,\"publisher\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/microsoft-project-2016-resources-with-multiple-pay-rates\\\/#primaryimage\"},\"thumbnailUrl\":\"http:\\\/\\\/www.pmvision.ca\\\/global\\\/wp-content\\\/uploads\\\/2018\\\/10\\\/Figure-1-Resources-Sheet-1024x407.jpg\",\"articleSection\":[\"MS.Project\",\"Project Management\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/microsoft-project-2016-resources-with-multiple-pay-rates\\\/\",\"url\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/microsoft-project-2016-resources-with-multiple-pay-rates\\\/\",\"name\":\"Microsoft Project 2016 | Resources With Multiple Pay Rates\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/microsoft-project-2016-resources-with-multiple-pay-rates\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/microsoft-project-2016-resources-with-multiple-pay-rates\\\/#primaryimage\"},\"thumbnailUrl\":\"http:\\\/\\\/www.pmvision.ca\\\/global\\\/wp-content\\\/uploads\\\/2018\\\/10\\\/Figure-1-Resources-Sheet-1024x407.jpg\",\"datePublished\":\"2018-07-06T16:33:32+00:00\",\"dateModified\":\"2018-12-15T04:40:01+00:00\",\"description\":\"In projects, you can have a single resource with multiple pay rates. Some resources might perform different tasks with different pay rates.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/microsoft-project-2016-resources-with-multiple-pay-rates\\\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/microsoft-project-2016-resources-with-multiple-pay-rates\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/microsoft-project-2016-resources-with-multiple-pay-rates\\\/#primaryimage\",\"url\":\"https:\\\/\\\/i0.wp.com\\\/www.pmvision.ca\\\/global\\\/wp-content\\\/uploads\\\/2018\\\/10\\\/Figure-1-Resources-Sheet.jpg?fit=1365%2C542&ssl=1\",\"contentUrl\":\"https:\\\/\\\/i0.wp.com\\\/www.pmvision.ca\\\/global\\\/wp-content\\\/uploads\\\/2018\\\/10\\\/Figure-1-Resources-Sheet.jpg?fit=1365%2C542&ssl=1\",\"width\":1365,\"height\":542,\"caption\":\"Microsoft Project 2016- Resource with multiple pay\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/microsoft-project-2016-resources-with-multiple-pay-rates\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Microsoft Project 2016 | Resources With Multiple Pay Rates\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/#website\",\"url\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/\",\"name\":\"PMVISION Global\",\"description\":\"Affordable Training, Global Reach\",\"publisher\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/#organization\",\"name\":\"PMVISION\",\"url\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/i0.wp.com\\\/www.pmvision.ca\\\/wp-content\\\/uploads\\\/2015\\\/07\\\/logo6.png?fit=418%2C114&ssl=1\",\"contentUrl\":\"https:\\\/\\\/i0.wp.com\\\/www.pmvision.ca\\\/wp-content\\\/uploads\\\/2015\\\/07\\\/logo6.png?fit=418%2C114&ssl=1\",\"width\":418,\"height\":114,\"caption\":\"PMVISION\"},\"image\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/#\\\/schema\\\/logo\\\/image\\\/\"},\"sameAs\":[\"https:\\\/\\\/www.facebook.com\\\/pmvisioninc\",\"https:\\\/\\\/x.com\\\/pmvisioninc\",\"https:\\\/\\\/www.linkedin.com\\\/company\\\/pmvision\",\"https:\\\/\\\/www.youtube.com\\\/channel\\\/UCKPT0nmE4Dnf2kFy--Sg5gg\\\/videos\u200e\"]},{\"@type\":\"Person\",\"@id\":\"\",\"url\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/author\\\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Microsoft Project 2016 | Resources With Multiple Pay Rates","description":"In projects, you can have a single resource with multiple pay rates. Some resources might perform different tasks with different pay rates.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/","og_locale":"en_US","og_type":"article","og_title":"Microsoft Project 2016 | Resources With Multiple Pay Rates","og_description":"In projects, you can have a single resource with multiple pay rates. Some resources might perform different tasks with different pay rates.","og_url":"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/","og_site_name":"PMVISION Global","article_publisher":"https:\/\/www.facebook.com\/pmvisioninc","article_published_time":"2018-07-06T16:33:32+00:00","article_modified_time":"2018-12-15T04:40:01+00:00","og_image":[{"url":"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-1-Resources-Sheet-1024x407.jpg","type":"","width":"","height":""}],"twitter_card":"summary_large_image","twitter_creator":"@pmvisioninc","twitter_site":"@pmvisioninc","twitter_misc":{"Written by":"","Est. reading time":"4 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/#article","isPartOf":{"@id":"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/"},"author":{"name":"","@id":""},"headline":"Microsoft Project 2016 | Resources With Multiple Pay Rates","datePublished":"2018-07-06T16:33:32+00:00","dateModified":"2018-12-15T04:40:01+00:00","mainEntityOfPage":{"@id":"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/"},"wordCount":714,"publisher":{"@id":"https:\/\/www.pmvision.ca\/global\/#organization"},"image":{"@id":"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/#primaryimage"},"thumbnailUrl":"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-1-Resources-Sheet-1024x407.jpg","articleSection":["MS.Project","Project Management"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/","url":"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/","name":"Microsoft Project 2016 | Resources With Multiple Pay Rates","isPartOf":{"@id":"https:\/\/www.pmvision.ca\/global\/#website"},"primaryImageOfPage":{"@id":"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/#primaryimage"},"image":{"@id":"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/#primaryimage"},"thumbnailUrl":"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-1-Resources-Sheet-1024x407.jpg","datePublished":"2018-07-06T16:33:32+00:00","dateModified":"2018-12-15T04:40:01+00:00","description":"In projects, you can have a single resource with multiple pay rates. Some resources might perform different tasks with different pay rates.","breadcrumb":{"@id":"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/#primaryimage","url":"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-1-Resources-Sheet.jpg?fit=1365%2C542&ssl=1","contentUrl":"https:\/\/i0.wp.com\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/10\/Figure-1-Resources-Sheet.jpg?fit=1365%2C542&ssl=1","width":1365,"height":542,"caption":"Microsoft Project 2016- Resource with multiple pay"},{"@type":"BreadcrumbList","@id":"https:\/\/www.pmvision.ca\/global\/microsoft-project-2016-resources-with-multiple-pay-rates\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/www.pmvision.ca\/global\/"},{"@type":"ListItem","position":2,"name":"Microsoft Project 2016 | Resources With Multiple Pay Rates"}]},{"@type":"WebSite","@id":"https:\/\/www.pmvision.ca\/global\/#website","url":"https:\/\/www.pmvision.ca\/global\/","name":"PMVISION Global","description":"Affordable Training, Global Reach","publisher":{"@id":"https:\/\/www.pmvision.ca\/global\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.pmvision.ca\/global\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/www.pmvision.ca\/global\/#organization","name":"PMVISION","url":"https:\/\/www.pmvision.ca\/global\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.pmvision.ca\/global\/#\/schema\/logo\/image\/","url":"https:\/\/i0.wp.com\/www.pmvision.ca\/wp-content\/uploads\/2015\/07\/logo6.png?fit=418%2C114&ssl=1","contentUrl":"https:\/\/i0.wp.com\/www.pmvision.ca\/wp-content\/uploads\/2015\/07\/logo6.png?fit=418%2C114&ssl=1","width":418,"height":114,"caption":"PMVISION"},"image":{"@id":"https:\/\/www.pmvision.ca\/global\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/pmvisioninc","https:\/\/x.com\/pmvisioninc","https:\/\/www.linkedin.com\/company\/pmvision","https:\/\/www.youtube.com\/channel\/UCKPT0nmE4Dnf2kFy--Sg5gg\/videos\u200e"]},{"@type":"Person","@id":"","url":"https:\/\/www.pmvision.ca\/global\/author\/"}]}},"jetpack_shortlink":"https:\/\/wp.me\/phsz9t-7Yo","jetpack_sharing_enabled":true,"jetpack_featured_media_url":"","_links":{"self":[{"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/posts\/30652","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/users\/354"}],"replies":[{"embeddable":true,"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/comments?post=30652"}],"version-history":[{"count":0,"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/posts\/30652\/revisions"}],"wp:attachment":[{"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/media?parent=30652"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/categories?post=30652"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/tags?post=30652"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}