{"id":31114,"date":"2018-12-10T19:36:45","date_gmt":"2018-12-10T23:36:45","guid":{"rendered":"https:\/\/www.pmvision.ca\/?p=31114"},"modified":"2018-12-14T23:25:04","modified_gmt":"2018-12-15T03:25:04","slug":"resource-leveling-in-microsoft-project","status":"publish","type":"post","link":"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/","title":{"rendered":"Resource Leveling in Microsoft Project &#8211; 1"},"content":{"rendered":"<p>Resource leveling can be a helpful tool when scheduling individual and multiple resources in projects. Leveling reschedules tasks to resolve over allocations. It can be useful in projects that don\u2019t have many task dependencies. By setting priorities to tasks it is possible to control and prioritize which tasks are the to be scheduled first.<\/p>\n<p>Here is a simple example to help illustrate how leveling can schedule tasks. Suppose you have a set of tasks for developing documentation as follows:<\/p>\n<div id=\"attachment_31163\" style=\"width: 767px\" class=\"wp-caption aligncenter\"><a href=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-leveling-in-MS-Project-1.bmp\"><img loading=\"lazy\" decoding=\"async\" aria-describedby=\"caption-attachment-31163\" class=\"size-full wp-image-31163\" src=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-leveling-in-MS-Project-1.bmp\" alt=\"Resource leveling in MS Project 1\" width=\"757\" height=\"137\" \/><\/a><p id=\"caption-attachment-31163\" class=\"wp-caption-text\">Resource leveling in MS Project &#8211; Example<\/p><\/div>\n<p>&nbsp;<\/p>\n<p>The tasks are all set to auto schedule. Assigning the same resource (Simon) to each task results in over allocation icon appearing in the indicator column.<\/p>\n<p>The usual way to overcome over allocations is to link the tasks together with Finish-Start relationships. But leveling offers an alternative if there no clear dependencies between tasks.<\/p>\n<blockquote><p><strong><a href=\"http:\/\/www.pmvision.ca\/global\/shop\/microsoft-project-training-courses-toronto\/\" target=\"_blank\" rel=\"noopener\">Learn MS.Project 2019\u00a0 Fundamentals in Toronto, Mississauga, Ottawa, &amp; Montreal<\/a><\/strong><\/p>\n<p><a href=\"http:\/\/www.pmvision.ca\/global\/shop\/advanced-microsoft-project-training-course\/\" target=\"_blank\" rel=\"noopener\"><strong>Learn Advanced Techniques in MS.Project 2019\u00a0 in Toronto, Mississauga, Ottawa, &amp; Montreal<\/strong><\/a><\/p>\n<p><strong><a href=\"http:\/\/www.pmvision.ca\/global\/shop\/pmi-sp-scheduling-professional-exam-prep-pmi-sp-training-courses\/\" target=\"_blank\" rel=\"noopener\">Learn Scheduling by taking our PMI-SP Scheduling Professional Exam Prep Class in Toronto<\/a><\/strong><\/p>\n<p><a href=\"http:\/\/www.pmvision.ca\/global\/shop\/pmi-sp-training-course-pmi-scheduling-professional\/\" target=\"_blank\" rel=\"noopener\"><strong>Learn Scheduling by taking our PMI-SP Scheduling Professional Online self-Paced Learning Course<\/strong><\/a><\/p><\/blockquote>\n<h2><\/h2>\n<h2><strong><span style=\"color: #008080;\">Leveling the Entire Project<\/span><\/strong><\/h2>\n<p>This option levels the entire project. Tasks get rescheduled to the first available date that results in no more over allocations. And yet there are no links, lags or constrains added. So how does levelling actually work?<\/p>\n<p>To schedule these tasks through resource leveling select <strong>Resource, Level All<\/strong><\/p>\n<div id=\"attachment_31164\" style=\"width: 1342px\" class=\"wp-caption aligncenter\"><a href=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-leveling-in-MS-Project-Level-All.bmp\"><img loading=\"lazy\" decoding=\"async\" aria-describedby=\"caption-attachment-31164\" class=\"size-full wp-image-31164\" src=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-leveling-in-MS-Project-Level-All.bmp\" alt=\"Resource leveling in MS Project - Level All\" width=\"1332\" height=\"172\" \/><\/a><p id=\"caption-attachment-31164\" class=\"wp-caption-text\">Resource leveling in MS Project &#8211; Level All<\/p><\/div>\n<p>&nbsp;<\/p>\n<p>We can see how Project does this rescheduling by looking at the Detail Gantt view.<br \/>\n<strong>Right click the View bar, select More Views, Detail Gantt<\/strong><\/p>\n<div id=\"attachment_31165\" style=\"width: 1224px\" class=\"wp-caption aligncenter\"><a href=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-leveling-in-MS-Project-Level-All-2.bmp\"><img loading=\"lazy\" decoding=\"async\" aria-describedby=\"caption-attachment-31165\" class=\"wp-image-31165 size-full\" src=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-leveling-in-MS-Project-Level-All-2.bmp\" alt=\"Resource leveling in MS Project - Level All 2\" width=\"1214\" height=\"213\" \/><\/a><p id=\"caption-attachment-31165\" class=\"wp-caption-text\">Resource leveling in MS Project &#8211; Level All 2<\/p><\/div>\n<p>&nbsp;<\/p>\n<p>In the Detail Gantt view there is an extra column called Leveling Delay. This is a delay applied to a task measured in elapsed time (edays). This elapsed time represents a date range including non-working days (weekends). In the example a leveling delay of 14 edays for task 3 causes it to be delayed by 10 working days. Note that as there are no dependencies the only critical task coloured pink is the final task.<\/p>\n<h2><\/h2>\n<h2><strong><span style=\"color: #008080;\">Clearing Leveling<\/span><\/strong><\/h2>\n<p>When you choose the Clear Leveling option the leveling delay values are reset to zero edays.<br \/>\n<strong>Select Resource, Clear Leveling<\/strong><\/p>\n<div id=\"attachment_31166\" style=\"width: 306px\" class=\"wp-caption aligncenter\"><a href=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-leveling-in-MS-Project-Clear-Leveling.bmp\"><img loading=\"lazy\" decoding=\"async\" aria-describedby=\"caption-attachment-31166\" class=\"size-full wp-image-31166\" src=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-leveling-in-MS-Project-Clear-Leveling.bmp\" alt=\"Resource leveling in MS Project - Clear Leveling\" width=\"296\" height=\"132\" \/><\/a><p id=\"caption-attachment-31166\" class=\"wp-caption-text\">Resource leveling in MS Project &#8211; Clear Leveling<\/p><\/div>\n<p>Choosing Entire project sets the Leveling Delay to zero for all tasks.<\/p>\n<p>&nbsp;<\/p>\n<h2><strong><span style=\"color: #008080;\">Resource Leveling by Priority<\/span><\/strong><\/h2>\n<p>To control which tasks are levelled you can set a task priority value for each task. Levelling the project then schedules tasks in order of priority. High priority tasks are scheduled to be carried out before low priority tasks. A value of between 0 and 1000 can be set where 1000 is the highest priority. The default priority value for task is 500.<\/p>\n<p>To set a task priority select <strong>Task, Information, Priority<\/strong><br \/>\nEnter a value for the priority.<br \/>\nInserting a priority column into the Gantt Chart makes it easier to update and view priority values.<\/p>\n<div id=\"attachment_31167\" style=\"width: 498px\" class=\"wp-caption aligncenter\"><a href=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-Leveling-by-Priority.bmp\"><img loading=\"lazy\" decoding=\"async\" aria-describedby=\"caption-attachment-31167\" class=\"size-full wp-image-31167\" src=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-Leveling-by-Priority.bmp\" alt=\"Resource Leveling by Priority\" width=\"488\" height=\"305\" \/><\/a><p id=\"caption-attachment-31167\" class=\"wp-caption-text\">Resource Leveling by Priority<\/p><\/div>\n<p>&nbsp;<\/p>\n<p>Selecting <strong>Level All<\/strong> schedules tasks to take place in order of priority. (Highest first)<\/p>\n<div id=\"attachment_31168\" style=\"width: 1297px\" class=\"wp-caption aligncenter\"><a href=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-Leveling-by-Priority-2.bmp\"><img loading=\"lazy\" decoding=\"async\" aria-describedby=\"caption-attachment-31168\" class=\"size-full wp-image-31168\" src=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-Leveling-by-Priority-2.bmp\" alt=\"Resource Leveling by Priority 2\" width=\"1287\" height=\"206\" \/><\/a><p id=\"caption-attachment-31168\" class=\"wp-caption-text\">Resource Leveling by Priority 2<\/p><\/div>\n<p>&nbsp;<\/p>\n<h2><strong><span style=\"color: #008080;\">Sorting by Priority<\/span><\/strong><\/h2>\n<p>After Leveling by priority it makes sence to resequence the tasks in the order that they are to be performed. This can be done by sorting by the Priority field from largest to smallest.<br \/>\nIn the exmple suppose two more tasks added, one with a high and one with a low priority. After adding these tasks and assigning them to the same resource the levelled plan looks as follows.<\/p>\n<div id=\"attachment_31169\" style=\"width: 593px\" class=\"wp-caption aligncenter\"><a href=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Sorting-by-Priority.bmp\"><img loading=\"lazy\" decoding=\"async\" aria-describedby=\"caption-attachment-31169\" class=\"size-full wp-image-31169\" src=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Sorting-by-Priority.bmp\" alt=\"\" width=\"583\" height=\"207\" \/><\/a><p id=\"caption-attachment-31169\" class=\"wp-caption-text\">Sorting by Priority<\/p><\/div>\n<p>&nbsp;<\/p>\n<p>It makes sense now to sort the plan either by Priority or by Start Date.<\/p>\n<div id=\"attachment_31170\" style=\"width: 1314px\" class=\"wp-caption aligncenter\"><a href=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Sorting-by-Priority-2.bmp\"><img loading=\"lazy\" decoding=\"async\" aria-describedby=\"caption-attachment-31170\" class=\"size-full wp-image-31170\" src=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Sorting-by-Priority-2.bmp\" alt=\"Sorting by Priority 2\" width=\"1304\" height=\"197\" \/><\/a><p id=\"caption-attachment-31170\" class=\"wp-caption-text\">Sorting by Priority 2<\/p><\/div>\n<p>&nbsp;<\/p>\n<p>Note that to sort by Priority and to also keep the task Id numbers in sequence select View, <strong>Sort, Sort By<\/strong><br \/>\nChoose to sort by Priority<br \/>\nCheck that<strong> Permanently renumber tasks<\/strong> is ticked before selecting Sort.<\/p>\n<div id=\"attachment_31171\" style=\"width: 565px\" class=\"wp-caption aligncenter\"><a href=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Sorting-by-Priority-3.bmp\"><img loading=\"lazy\" decoding=\"async\" aria-describedby=\"caption-attachment-31171\" class=\"size-full wp-image-31171\" src=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Sorting-by-Priority-3.bmp\" alt=\"Sorting by Priority 3\" width=\"555\" height=\"364\" \/><\/a><p id=\"caption-attachment-31171\" class=\"wp-caption-text\">Sorting by Priority 3<\/p><\/div>\n<p>&nbsp;<\/p>\n<p>Read Part 2 <a href=\"http:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project-2\/\" target=\"_blank\" rel=\"noopener\"><strong>Resource Leveling in Microsoft Project &#8211; 2<\/strong><\/a><\/p>\n<p>&nbsp;<\/p>\n<blockquote><p><strong><a href=\"http:\/\/www.pmvision.ca\/global\/shop\/microsoft-project-training-courses-toronto\/\" target=\"_blank\" rel=\"noopener\">Learn MS.Project 2019\u00a0 Fundamentals in Toronto, Mississauga, Ottawa, &amp; Montreal<\/a><\/strong><\/p>\n<p><a href=\"http:\/\/www.pmvision.ca\/global\/shop\/advanced-microsoft-project-training-course\/\" target=\"_blank\" rel=\"noopener\"><strong>Learn Advanced Techniques in MS.Project 2019\u00a0 in Toronto, Mississauga, Ottawa, &amp; Montreal<\/strong><\/a><\/p>\n<p><strong><a href=\"http:\/\/www.pmvision.ca\/global\/shop\/pmi-sp-scheduling-professional-exam-prep-pmi-sp-training-courses\/\" target=\"_blank\" rel=\"noopener\">Learn Scheduling by taking our PMI-SP Scheduling Professional Exam Prep Class in Toronto<\/a><\/strong><\/p>\n<p><a href=\"http:\/\/www.pmvision.ca\/global\/shop\/pmi-sp-training-course-pmi-scheduling-professional\/\" target=\"_blank\" rel=\"noopener\"><strong>Learn Scheduling by taking our PMI-SP Scheduling Professional Online self-Paced Learning Course<\/strong><\/a><\/p><\/blockquote>\n","protected":false},"excerpt":{"rendered":"<p>Resource leveling can be a helpful tool when scheduling individual and multiple resources in projects. Leveling reschedules tasks to resolve over allocations. It can be useful in projects that don\u2019t have many task dependencies. By setting priorities to tasks it is possible to control and prioritize which tasks are the to be scheduled first. Here [&hellip;]<\/p>\n","protected":false},"author":354,"featured_media":0,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_jetpack_newsletter_access":"","_jetpack_dont_email_post_to_subs":false,"_jetpack_newsletter_tier_id":0,"_jetpack_memberships_contains_paywalled_content":false,"_jetpack_feature_clip_id":0,"_jetpack_memberships_contains_paid_content":false,"footnotes":"","jetpack_post_was_ever_published":false},"categories":[65,18],"tags":[],"class_list":["post-31114","post","type-post","status-publish","format-standard","hentry","category-ms-project","category-pm"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v28.7 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Resource Leveling in Microsoft Project - 1<\/title>\n<meta name=\"description\" content=\"Resource leveling can be a helpful tool when scheduling individual and multiple resources in projects. Leveling reschedules tasks to resolve over allocations.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Resource Leveling in Microsoft Project - 1\" \/>\n<meta property=\"og:description\" content=\"Resource leveling can be a helpful tool when scheduling individual and multiple resources in projects. Leveling reschedules tasks to resolve over allocations.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/\" \/>\n<meta property=\"og:site_name\" content=\"PMVISION Global\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/pmvisioninc\" \/>\n<meta property=\"article:published_time\" content=\"2018-12-10T23:36:45+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2018-12-15T03:25:04+00:00\" \/>\n<meta property=\"og:image\" content=\"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-leveling-in-MS-Project-1.bmp\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:creator\" content=\"@pmvisioninc\" \/>\n<meta name=\"twitter:site\" content=\"@pmvisioninc\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"4 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/resource-leveling-in-microsoft-project\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/resource-leveling-in-microsoft-project\\\/\"},\"author\":{\"name\":\"\",\"@id\":\"\"},\"headline\":\"Resource Leveling in Microsoft Project &#8211; 1\",\"datePublished\":\"2018-12-10T23:36:45+00:00\",\"dateModified\":\"2018-12-15T03:25:04+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/resource-leveling-in-microsoft-project\\\/\"},\"wordCount\":778,\"publisher\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/resource-leveling-in-microsoft-project\\\/#primaryimage\"},\"thumbnailUrl\":\"http:\\\/\\\/www.pmvision.ca\\\/global\\\/wp-content\\\/uploads\\\/2018\\\/12\\\/Resource-leveling-in-MS-Project-1.bmp\",\"articleSection\":[\"MS.Project\",\"Project Management\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/resource-leveling-in-microsoft-project\\\/\",\"url\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/resource-leveling-in-microsoft-project\\\/\",\"name\":\"Resource Leveling in Microsoft Project - 1\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/resource-leveling-in-microsoft-project\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/resource-leveling-in-microsoft-project\\\/#primaryimage\"},\"thumbnailUrl\":\"http:\\\/\\\/www.pmvision.ca\\\/global\\\/wp-content\\\/uploads\\\/2018\\\/12\\\/Resource-leveling-in-MS-Project-1.bmp\",\"datePublished\":\"2018-12-10T23:36:45+00:00\",\"dateModified\":\"2018-12-15T03:25:04+00:00\",\"description\":\"Resource leveling can be a helpful tool when scheduling individual and multiple resources in projects. Leveling reschedules tasks to resolve over allocations.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/resource-leveling-in-microsoft-project\\\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/resource-leveling-in-microsoft-project\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/resource-leveling-in-microsoft-project\\\/#primaryimage\",\"url\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/wp-content\\\/uploads\\\/2018\\\/12\\\/Resource-leveling-in-MS-Project-1.bmp\",\"contentUrl\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/wp-content\\\/uploads\\\/2018\\\/12\\\/Resource-leveling-in-MS-Project-1.bmp\",\"width\":757,\"height\":137,\"caption\":\"Resource leveling in MS Project - Example\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/resource-leveling-in-microsoft-project\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Resource Leveling in Microsoft Project &#8211; 1\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/#website\",\"url\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/\",\"name\":\"PMVISION Global\",\"description\":\"Affordable Training, Global Reach\",\"publisher\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/#organization\",\"name\":\"PMVISION\",\"url\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/i0.wp.com\\\/www.pmvision.ca\\\/wp-content\\\/uploads\\\/2015\\\/07\\\/logo6.png?fit=418%2C114&ssl=1\",\"contentUrl\":\"https:\\\/\\\/i0.wp.com\\\/www.pmvision.ca\\\/wp-content\\\/uploads\\\/2015\\\/07\\\/logo6.png?fit=418%2C114&ssl=1\",\"width\":418,\"height\":114,\"caption\":\"PMVISION\"},\"image\":{\"@id\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/#\\\/schema\\\/logo\\\/image\\\/\"},\"sameAs\":[\"https:\\\/\\\/www.facebook.com\\\/pmvisioninc\",\"https:\\\/\\\/x.com\\\/pmvisioninc\",\"https:\\\/\\\/www.linkedin.com\\\/company\\\/pmvision\",\"https:\\\/\\\/www.youtube.com\\\/channel\\\/UCKPT0nmE4Dnf2kFy--Sg5gg\\\/videos\u200e\"]},{\"@type\":\"Person\",\"@id\":\"\",\"url\":\"https:\\\/\\\/www.pmvision.ca\\\/global\\\/author\\\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Resource Leveling in Microsoft Project - 1","description":"Resource leveling can be a helpful tool when scheduling individual and multiple resources in projects. Leveling reschedules tasks to resolve over allocations.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/","og_locale":"en_US","og_type":"article","og_title":"Resource Leveling in Microsoft Project - 1","og_description":"Resource leveling can be a helpful tool when scheduling individual and multiple resources in projects. Leveling reschedules tasks to resolve over allocations.","og_url":"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/","og_site_name":"PMVISION Global","article_publisher":"https:\/\/www.facebook.com\/pmvisioninc","article_published_time":"2018-12-10T23:36:45+00:00","article_modified_time":"2018-12-15T03:25:04+00:00","og_image":[{"url":"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-leveling-in-MS-Project-1.bmp","type":"","width":"","height":""}],"twitter_card":"summary_large_image","twitter_creator":"@pmvisioninc","twitter_site":"@pmvisioninc","twitter_misc":{"Written by":"","Est. reading time":"4 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/#article","isPartOf":{"@id":"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/"},"author":{"name":"","@id":""},"headline":"Resource Leveling in Microsoft Project &#8211; 1","datePublished":"2018-12-10T23:36:45+00:00","dateModified":"2018-12-15T03:25:04+00:00","mainEntityOfPage":{"@id":"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/"},"wordCount":778,"publisher":{"@id":"https:\/\/www.pmvision.ca\/global\/#organization"},"image":{"@id":"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/#primaryimage"},"thumbnailUrl":"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-leveling-in-MS-Project-1.bmp","articleSection":["MS.Project","Project Management"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/","url":"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/","name":"Resource Leveling in Microsoft Project - 1","isPartOf":{"@id":"https:\/\/www.pmvision.ca\/global\/#website"},"primaryImageOfPage":{"@id":"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/#primaryimage"},"image":{"@id":"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/#primaryimage"},"thumbnailUrl":"http:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-leveling-in-MS-Project-1.bmp","datePublished":"2018-12-10T23:36:45+00:00","dateModified":"2018-12-15T03:25:04+00:00","description":"Resource leveling can be a helpful tool when scheduling individual and multiple resources in projects. Leveling reschedules tasks to resolve over allocations.","breadcrumb":{"@id":"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/#primaryimage","url":"https:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-leveling-in-MS-Project-1.bmp","contentUrl":"https:\/\/www.pmvision.ca\/global\/wp-content\/uploads\/2018\/12\/Resource-leveling-in-MS-Project-1.bmp","width":757,"height":137,"caption":"Resource leveling in MS Project - Example"},{"@type":"BreadcrumbList","@id":"https:\/\/www.pmvision.ca\/global\/resource-leveling-in-microsoft-project\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/www.pmvision.ca\/global\/"},{"@type":"ListItem","position":2,"name":"Resource Leveling in Microsoft Project &#8211; 1"}]},{"@type":"WebSite","@id":"https:\/\/www.pmvision.ca\/global\/#website","url":"https:\/\/www.pmvision.ca\/global\/","name":"PMVISION Global","description":"Affordable Training, Global Reach","publisher":{"@id":"https:\/\/www.pmvision.ca\/global\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.pmvision.ca\/global\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/www.pmvision.ca\/global\/#organization","name":"PMVISION","url":"https:\/\/www.pmvision.ca\/global\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.pmvision.ca\/global\/#\/schema\/logo\/image\/","url":"https:\/\/i0.wp.com\/www.pmvision.ca\/wp-content\/uploads\/2015\/07\/logo6.png?fit=418%2C114&ssl=1","contentUrl":"https:\/\/i0.wp.com\/www.pmvision.ca\/wp-content\/uploads\/2015\/07\/logo6.png?fit=418%2C114&ssl=1","width":418,"height":114,"caption":"PMVISION"},"image":{"@id":"https:\/\/www.pmvision.ca\/global\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/pmvisioninc","https:\/\/x.com\/pmvisioninc","https:\/\/www.linkedin.com\/company\/pmvision","https:\/\/www.youtube.com\/channel\/UCKPT0nmE4Dnf2kFy--Sg5gg\/videos\u200e"]},{"@type":"Person","@id":"","url":"https:\/\/www.pmvision.ca\/global\/author\/"}]}},"jetpack_shortlink":"https:\/\/wp.me\/phsz9t-85Q","jetpack_sharing_enabled":true,"jetpack_featured_media_url":"","_links":{"self":[{"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/posts\/31114","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/users\/354"}],"replies":[{"embeddable":true,"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/comments?post=31114"}],"version-history":[{"count":0,"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/posts\/31114\/revisions"}],"wp:attachment":[{"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/media?parent=31114"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/categories?post=31114"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.pmvision.ca\/global\/wp-json\/wp\/v2\/tags?post=31114"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}